top of page
background_edited.png

PROJECTS

Our highly trained and reliable team have attained Nationally Accredited competencies with the experience to efficiently deliver a broad range of projects in a safe & environmentally conscious manner, whilst maintaining the highest level of quality.

Western Sydney Airport

Project: Western Sydney Airport

Client:  Duratec 

 

Scope: Trenching and backfilling 11 km of the 450 mm diameter fuel main ranging from 2 m to 6 m deep in some areas. This also included ITS pit and conduit installation and FRP valve pit structures.

​

​

  • 11 km of ITS pit and conduit installation

  • FRP valve pit structures

  • Over 10,000 m³ of concrete poured

  • Extensive rock excavation (over 30,000 m³)

  • Challenging staging plans and weather conditions surmounted

  • Highest standards of backfilling achieved (Airport Taxiway – Level 1 GITA)

​

​

This demanding project showcases Kane Civil’s expertise in trenching and bulk earthworks while meeting project deadlines and maintaining the highest standards of quality and safety.

Port Botany

Project: WestConnex 3B – Iron Cove Link

Client: John Holland and CPB Contractors JV

​

Scope: Kane Civil had been engaged to carry out multiple scopes, including installation of underground services and general earthworks in challenging conditions.

​​​

  • Stormwater and ITS installation under ROLs and within the site boundary

  • Cut and cover staging excavation

  • Bulk and detailed excavation

  • Rock sawing

  • Wall trimming

  • General plant and labour hire

​

​One of the notable achievements during this project was the successful collaboration between Kane Civil and the ICL team. Working directly together, the teams developed a sequence of works for drainage installation on the live carriageway of Victoria Road during ROL times. This collaboration helped minimise local impact due to noise, dust, and vibration, despite challenging road conditions.

Project: Sydney Metro – Marrickville Dive

Client: John Holland and CPB Contractors

​

Scope: Bulk and detailed earthworks, including the installation of an intricate drainage system throughout.

​

  • Demolition of 2,747 tonnes of heavily reinforced concrete

  • Rock sawing 1,879 m

  • Excavation of 4,170 tonnes of rock

  • Installation of 3,835 m of stormwater drainage FRC pipes

  • Pouring 1,411 m³ of concrete

​

The Marrickville dive site played a pivotal role in the launch and support of two tunnel boring machines for the Sydney Metro project. Kane Civil was entrusted with the task of removing a heavily reinforced concrete slab and commencing drainage installation after the TBMs' launch.

Overcoming the unique constraints of the dive site, Kane Civil successfully navigated the distinct challenges of this project, ensuring the safe and efficient progress of the broader Sydney Metro project.

MARRICKVILLE SYDNEY METRO
ROZELLE ICL WESTCONNEX

Project: WestConnex 3B – Sydney Trains Switching Substation Rozelle

Client: Gartner Rose


Scope: All civil works included new kerbs, installation of bollards, earthworks, and new storm drainage.


Kane Civil successfully completed the civil scope on the new Sydney Trains Switching Substation for Gartner Rose within the Rozelle Rail Yards as part of the WestConnex 3B Rozelle Interchange Project. Significant electrical conduits were also installed to allow the commissioning of the substation.

SY9 Substation 

Client: Degnan Group

​

Scope:  Kane Civil Engineering was engaged by Degnan to deliver civil and foundation works for a new 33kV substation within a legacy industrial, asbestos-contaminated environment. 

​

•    Energy & Utilities Infrastructure
•    Bulk Earthworks
•    Screw Piling
•    Detailed Excavation
•    Conduits & Services
•    Stormwater Installation
•    Contaminated Ground Management


Challenges included managing undocumented legacy services and shallow groundwater conditions, requiring coordination, protection, relocation, and efficient groundwater management strategies. Through proactive planning and close collaboration with Degnan, Kane Civil successfully delivered critical early works, enabling the safe and timely construction of the substation.
 

Project: Warringah Freeway Upgrade

Client: CPB and DTI JV


Scope: Kane Civil have been engaged by CPBDTIJV to deliver a varied scope, including the following:


•    Bulk rock excavations including 20,000 t removed from the Ernest Street underpass 
•    Detailed rock cuts including rock sawing, hammering and pineapple works 
•    Sandstone walls cut to tolerance 
•    Stormwater drainage installation 
•    ITS pit and conduit installation 
•    ASP1 accredited HV pit and conduit installation 
•    Pavement construction 


The Warringah Freeway Upgrade is revitalising a 4-kilometre corridor through North Sydney, delivering extensive road, bridge and interchange work to improve 

Project: Sydney Terminal Building Revitalisation Project

Client: Gartner Rose

​

Scope: Kane Civil have been engaged by Gartner Rose to deliver the civil scope on this iconic project, which includes the following:

  • Demolition and removal of the old access ramp

  • Bulk and detailed earthworks

  • Limited access due to light rail operating hours means all material had to be imported/exported during approved restricted windows

  • Stormwater and CSR works

The STBRP will rejuvenate Central Station’s Sydney Terminal Building, improving the customer experience and creating a vibrant and modern environment for passengers and visitors.

Project: Menangle Park Transmission Substation

Client: Haslin Constructions

​

Scope: Electrical Conduits & Pits, Stormwater Infrastructure, Bulk Earthworks, Site Level Raise

 

Kane Civil Engineering is delivering critical civil and underground infrastructure works for the development of a new 33kV electrical substation for Haslin. The project involves the installation of extensive electrical conduit networks and associated service pits, construction of stormwater drainage systems including pipes and pits, and bulk earthworks to import engineered fill and achieve required finished surface levels across the site.

 

Works are being delivered in a live construction environment, requiring careful sequencing and coordination to support ongoing structural and electrical installation activities. Kane Civil has implemented a structured earthworks and services delivery approach to ensure the formation of a stable building platform while maintaining programme certainty and compliance with project specifications. Our team’s experience in utility infrastructure enables efficient integration of underground services, ensuring constructability, accuracy, and alignment with the broader design intent.

Project: Western Sydney Airport Substation

Client: Haslin Constructions

​

Scope: Electrical Conduits & Pits, Stormwater Infrastructure, Bulk & Detailed Earthworks

Kane Civil was engaged by Haslin Constructions to carry out the civil scope for the construction of a brand-new, 132kV Digital Transmission Substation at Badgerys Creek in Western Sydney. This facility provides electricity to the new Western Sydney International Airport as part of the NSW Government’s mammoth Western Sydney Aerotropolis project.

 

As the largest indoor transmission substation in the Endeavour Network, there were some unique changes. Our team installed a substantial conduit network to service this building, along with in-ground drainage and large retention tanks, along with GPTs.

 

Through disciplined planning, strong site management, and a focus on safety and environmental performance, Kane Civil continues to support the delivery of essential energy infrastructure while maintaining high standards of quality and technical execution.

Project: Eastern Creek Speedway

Client: Abergeldie Complex Infrastructures


Scope: Kane Civil had been engaged to carry out extensive conduit and pit installation throughout the project, along with additional detailed earthworks. Overall, this included approximately 4,000 lm of conduit and 129 precast pits.

 

This project delivered a new clay-based racetrack catering to both speedway cars and motorcycles, ensuring an enhanced racing experience. A new grandstand, terraced seating for 7,000 spectators, and comprehensive amenities including corporate boxes, food, beverage, and merchandise outlets. Construction of 2,800 new parking spaces and dual vehicle access via a new intersection built off Ferrers Road. Construction of a dedicated competitor pit area, including workshops, garages, and trackside support services.

Project: Sydenham Station Junction Upgrade (SSJ)

Client: John Holland and Laing O’Rourke JV

​

Scope: The completion of a bulk and detailed earthworks package including ground stabilisation. In addition, KC carried out FRP works which included cess drains adjacent to live track, retaining walls, stitch pours, and trackside foundations. Our experienced team also positioned 800 m of precast retaining walls weighing between 5 and 12 t each with the use of our in-house cranage equipment, all achieved under Level 5 protection. Other activities include drainage, CSR and multiple ULX installations.

 

SSJ is a critical part of the transformation of the overall Sydney Metro City & Southwest project and is a key area of interface where the new metro meets the existing Sydney Trains networks.

KANE-CIVIL_Final_CV_02112016.png
  • LinkedIn
  • Facebook
  • Instagram

© KANE CIVIL 2023

bottom of page